  "url": "https://openlegislation.uk/keadby-3-carbon-capture-equipped-gas-fired-generating-station-order-2022/schedule-2/paragraph-36",
  "json_url": "https://openlegislation.uk/keadby-3-carbon-capture-equipped-gas-fired-generating-station-order-2022/schedule-2/paragraph-36.json",
  "legislation": "uksi/2022/1396",
  "legislation_title": "The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022",
  "legislation_url": "https://openlegislation.uk/keadby-3-carbon-capture-equipped-gas-fired-generating-station-order-2022",
  "path": "schedule/2/paragraph/36",
  "kind": "paragraph",
  "number": "36",
  "heading": "Local liaison committee",
  "text": "(1) No part of the authorised development may commence, save for the permitted preliminary works and Works Nos. 9B and 9C, until the undertaker has established a committee to liaise with local residents and organisations to keep them informed on matters relating to the construction and commissioning of the authorised development (a ‘local liaison committee’).\n(2) The undertaker must invite the relevant planning authority, all parish councils within close proximity to the authorised development, and other relevant interest groups, as may be agreed with the relevant planning authority, to nominate representatives to join the local liaison committee.\n(3) The undertaker must provide a full secretariat service and supply an appropriate venue (which may include online conferencing with telephone dial in) for the local liaison committee meetings to take place.\n(4) The local liaison committee must—\n(a) include representatives of the undertaker;\n(b) meet every other month, starting in the month prior to commencement of the authorised development, until the completion of construction, testing and commissioning works unless otherwise agreed by the majority of the members of the local liaison committee; and\n(c) during the operation of the authorised development meet once a year unless otherwise agreed by the majority of the members of the local liaison committee.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 2 para. 36 in force at 29.12.2022, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2022/1396/schedule/2/paragraph/36",
    "retrieved_at": "2026-10-28T21:51:18.993466+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}