# The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022, Schedule 5: ACCESS - THOSE PARTS OF THE ACCESS TO BE MAINTAINED AT THE PUBLIC EXPENSE

Extent: E+W+S

Table 3
(1)
Area
(2)
Street
(3)
Description of relevant part of access
In the Borough of North Lincolnshire
A18
That part of each of the two accesses hatched blue and referenced at points marked A and C on sheet 1 of the access and rights of way plan

---