# The Kemsley Mill K4 Combined Heat and Power Generating Station Order 2019, Note: Explanatory note


(This note is not part of the Order)
This Order authorises DS Smith Paper Limited to construct, operate and maintain a new combined heat and power generating station at the Kemsley Mill and carry out all associated works. The Order provides for the decommissioning of the existing generating station on the site.
The Order also makes provision in connection with the maintenance of the authorised development.
A copy of the plans, environmental statement and other documents mentioned in this Order and certified in accordance with article 12 of this Order (certification of plans, etc.) may be inspected free of charge during working hours at Kemsley Paper Mill, Sittingbourne, Kent, ME10 2TD.

---
Source: https://www.legislation.gov.uk/uksi/2019/1091/note (the official version)
Page: https://openlegislation.uk/kemsley-mill-k4-combined-heat-and-power-generating-station-order-2019/note
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.