# The Kemsley Mill K4 Combined Heat and Power Generating Station Order 2019, Paragraph 10: Construction hours


(1) Subject to sub-paragraph (2), no construction works are to take place except between—
(a) 07:00 and 19:00 Monday to Friday; and
(b) 07:00 and 16:00 on Saturdays, Sundays and public holidays,
unless otherwise agreed by the relevant planning authority.
(2) Emergency works are permitted outside the hours referred to in sub-paragraph (1).
(3) Any emergency works carried out under sub-paragraph (2) must be notified to the relevant planning authority within 72 hours of their commencement.

---
Source: https://www.legislation.gov.uk/uksi/2019/1091/schedule/2/paragraph/10 (the official version)
Page: https://openlegislation.uk/kemsley-mill-k4-combined-heat-and-power-generating-station-order-2019/schedule-2/paragraph-10
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.