# The Kemsley Mill K4 Combined Heat and Power Generating Station Order 2019, Paragraph 15: Piling


(1) No part of the authorised development may be commenced until a piling risk assessment for that part has been submitted to and approved by the relevant planning authority in consultation with the Environment Agency.
(2) Construction works for the authorised development must be carried out in accordance with the approved piling method and agreed risk management for that method as set out in the approved piling risk assessment.

---