# The Kemsley Mill K4 Combined Heat and Power Generating Station Order 2019, Paragraph 16: Piling


(1) No impact piling associated with the authorised development shall take place during the months of January and February.
(2) No more than ten days of impact piling associated with the authorised development, whether consecutive or otherwise, shall take place in the period consisting of the months of November and December.
(3) This requirement does not restrict impact piling associated with the authorised development between the months of March and October inclusive.

---
Source: https://www.legislation.gov.uk/uksi/2019/1091/schedule/2/paragraph/16 (the official version)
Page: https://openlegislation.uk/kemsley-mill-k4-combined-heat-and-power-generating-station-order-2019/schedule-2/paragraph-16
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

