{
  "url": "https://openlegislation.uk/kemsley-mill-k4-combined-heat-and-power-generating-station-order-2019/schedule-2/paragraph-7",
  "json_url": "https://openlegislation.uk/kemsley-mill-k4-combined-heat-and-power-generating-station-order-2019/schedule-2/paragraph-7.json",
  "legislation": "uksi/2019/1091",
  "legislation_title": "The Kemsley Mill K4 Combined Heat and Power Generating Station Order 2019",
  "legislation_url": "https://openlegislation.uk/kemsley-mill-k4-combined-heat-and-power-generating-station-order-2019",
  "path": "schedule/2/paragraph/7",
  "kind": "paragraph",
  "number": "7",
  "heading": "Construction Environmental Management Plan",
  "text": "(1) No part of the authorised development may be commenced until a CEMP for that part has been submitted to and approved by the relevant planning authority in consultation with the highway authority.\n(2) The CEMP, which must specify measures to mitigate the impacts of construction works, must be substantially in accordance with the outline CEMP.\n(3) Construction works for the authorised development must be carried out in accordance with the approved CEMP for that part.",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2019/1091/schedule/2/paragraph/7",
    "retrieved_at": "2026-10-28T22:39:01.220481+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}