Paragraph 8 Construction Traffic Management Plan
No part of the authorised development may be commenced until a Construction Traffic Management Plan for that part has been submitted to and approved by the relevant planning authority in consultation with the highway authority.
The Construction Traffic Management Plan must:
specify measures to mitigate the impacts of construction traffic during the construction works;
be substantially in accordance with section 4.8 of the environmental statement; and
include a travel plan for contractors that sets out measures to control the arrival and departure of construction staff during peak travel times (08:00 to 09:00 and 17:00 to 18:00 on weekdays).
Construction works for the authorised development must be carried out in accordance with the approved Construction Traffic Management Plan for that part.