# The Keuper Underground Gas Storage Facility Order 2017, Paragraph 7: Accesses to works

Extent: E+W

(1) No part of the authorised development may be commenced until written details of the siting, design and layout of any new permanent or temporary means of access to a highway for that part has been submitted to and approved in writing by the relevant planning authority.
(2) The highway accesses must be constructed in accordance with the approved details.

---
Source: https://www.legislation.gov.uk/uksi/2017/433/schedule/2/paragraph/7 (the official version)
Page: https://openlegislation.uk/keuper-underground-gas-storage-facility-order-2017/schedule-2/paragraph-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.