# The Keuper Underground Gas Storage Facility Order 2017, Paragraph 40

Extent: E+W

The undertaker must repay to the Canal & River Trust in accordance with the Canal & River Trust’s code of practice all reasonable fees, costs, charges and expenses reasonably incurred by the Canal & River Trust-
(a) in constructing any part of a specified work on behalf of the undertaker or in constructing any protective works under the provisions of paragraph 27(5) including, in respect of any permanent protective works, a capitalised sum representing the cost of maintaining and renewing those works;
(b) in respect of the approval by the engineer of plans submitted by the undertaker and the supervision by him of the construction of a specified work or any protective works;
(c) in respect of the employment or procurement of the services of any persons whom it must be reasonably necessary to appoint for inspecting, signalling, watching and lighting Canal & River Trust property and for preventing, so far as may be reasonably practicable, interference, obstruction, danger or incident arising from the construction or failure of a specified work or any protective works;
(d) in respect of any additional temporary lighting of the Canal & River Trust property in the vicinity of the specified works or any protective works, being lighting made reasonably necessary by reason or in consequence of the construction or failure of a specified work or protective work; and
(e) In bringing the specified works or any protective works to the notice of users of the Canal & River Trust’s network.

---
Source: https://www.legislation.gov.uk/uksi/2017/433/schedule/9/paragraph/40 (the official version)
Page: https://openlegislation.uk/keuper-underground-gas-storage-facility-order-2017/schedule-9/paragraph-40
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.