# The Knottingley Power Plant Order 2015, Paragraph 14: Contaminated land and groundwater – known contamination on the site of the generating station

Extent: E+W

The part of the authorised development comprising the generating station must not commence until the remediation permission has been implemented in full and a verification report under Requirement 13(5) has been submitted to and approved in writing by the relevant planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2015/680/schedule/1/paragraph/14 (the official version)
Page: https://openlegislation.uk/knottingley-power-plant-order-2015/schedule-1/paragraph-14
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.