  "url": "https://openlegislation.uk/knottingley-power-plant-order-2015/schedule-1/paragraph-15",
  "json_url": "https://openlegislation.uk/knottingley-power-plant-order-2015/schedule-1/paragraph-15.json",
  "legislation": "uksi/2015/680",
  "legislation_title": "The Knottingley Power Plant Order 2015",
  "legislation_url": "https://openlegislation.uk/knottingley-power-plant-order-2015",
  "path": "schedule/1/paragraph/15",
  "kind": "paragraph",
  "number": "15",
  "heading": "Archaeology",
  "text": "(1) No part of the authorised development may commence until for that part a written scheme for the investigation of areas of archaeological interest has been submitted to and approved in writing by the relevant planning authority.\n(2) The scheme must identify areas where field work and/or a watching brief are required, and the measures to be taken to protect, record or preserve any significant archaeological remains that may be found.\n(3) Any archaeological works or watching brief implemented under the scheme must be by a suitably qualified person or body approved in writing by the relevant planning authority.\n(4) Any archaeological works or watching brief must be implemented in accordance with the approved scheme.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 1 para. 15 in force at 1.4.2015, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2015/680/schedule/1/paragraph/15",
    "retrieved_at": "2026-10-28T23:42:46.530680+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}