A facility must be provided and maintained within Work No. 1 to enable steam pass-outs and/or hot water pass-outs and reserve space for the provision of water pressurisation, heating and pumping systems for off-site users of process and space heating and its later connection to such systems should a commercial arrangement be identified for combined heat and power which is economically viable.

---