# The Knottingley Power Plant Order 2015, Paragraph 9: Footpath/Public Rights of Way diversions

Extent: E+W

(1) No part of the authorised development may commence until a written public rights of way management plan for any sections of public rights of way shown to be extinguished or temporarily closed on the public rights of way temporary closures and permanent stopping up plan for that part has been approved in writing by the relevant planning authority in consultation with the relevant highway authority.
(2) The public rights of way management plan for the relevant part must include details of and a specification for the provisions of the temporary bridleway to be provided as part of Work No. 9.
(3) The public rights of way management plan and the provision of the temporary bridleway must thereafter be implemented as approved.

---
Source: https://www.legislation.gov.uk/uksi/2015/680/schedule/1/paragraph/9 (the official version)
Page: https://openlegislation.uk/knottingley-power-plant-order-2015/schedule-1/paragraph-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.