# The Knottingley Power Plant Order 2015, Part 1: Claimed public right of way to be extinguished for which a replacement will be provided

Extent: E+W

(1)
(2)
(3)
(4)
Area
Public right of way to be stopped up
Extent of stopping up
Temporary bridleway
Wakefield Metropolitan
Claimed public bridleway along Common Lane
So much of Common Lane as is shown market by a green dashed line on the public rights of way temporary closures and permanent stopping up plan
The temporary bridleway described in Work No. 9 in Part 1 of Schedule 1 and shown coloured yellow on the plan

---
Source: https://www.legislation.gov.uk/uksi/2015/680/schedule/4/part/1 (the official version)
Page: https://openlegislation.uk/knottingley-power-plant-order-2015/schedule-4/part-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.