# The Knottingley Power Plant Order 2015, Part 3: Rights of way for which no replacement will be provided during temporary closure

Extent: E+W

(1)
(2)
(3)
Area
Footpath to be temporarily closed
Extent of temporary closure
Wakefield District
Claimed public bridleway along Common Lane and leading onto a track connecting to Beal Lane
As shown marked by a pink dashed line on the public rights of way temporary closures and permanent stopping up plan
Wakefield District
Claimed public bridleway along Southmoor Lane
As shown marked by a pink dashed line on the public rights of way temporary closures and permanent stopping up plan

---