# The Labour Relations Agency Arbitration Scheme Order (Northern Ireland) 2012, Paragraph 102: Correction by the arbitrator


Any application by a party for the exercise of this power must be made through the LRA within 28 days beginning with the date the award was sent to that party by the LRA.

---
Source: https://www.legislation.gov.uk/nisr/2012/301/schedule/paragraph/102 (the official version)
Page: https://openlegislation.uk/labour-relations-agency-arbitration-scheme-order-northern-ireland-2012/schedule/paragraph-102
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.