# The Lake Lothing (Lowestoft) Third Crossing Order 2020, Paragraph 18

Extent: E+W

In this Part of this Schedule—
“the Agency” means the Environment Agency;
“completion” in relation to a specified work means the date on which it is brought into use;
“construction” includes execution, placing, altering, replacing, relaying, removal and excavation and “construct” and “constructed” have corresponding meanings;
“drainage work” includes any land which provides or is expected to provide flood storage capacity for Lake Lothing and any bank, wall, embankment or other structure, or any appliance constructed or used for land drainage, flood defence or tidal monitoring;
“the fishery” means Lake Lothing;
“plans” includes sections, drawings, sediment risk analysis, specifications, calculations and method statements;
“specified work” means so much of any work or operation authorised by this Order as is in, on, under, over or within 8 metres of a drainage work or is otherwise likely to—
(a)affect any drainage work or the volumetric rate of flow of water in or flowing to or from any drainage work;
(b)affect the flow, purity or quality of water in Lake Lothing and any other watercourse or other surface waters or ground water;
(c)cause obstruction to the free passage of fish or damage to the fishery;
(d)affect the conservation, distribution or use of water resources; or
(e)affect the conservation value of Lake Lothing and habitats in its immediate vicinity; and
“watercourse” includes all rivers, streams, ditches, drains, cuts, culverts, dykes, sluices, basins, sewers and passages through which water flows except a public sewer.

---
Source: https://www.legislation.gov.uk/uksi/2020/474/schedule/13/paragraph/18 (the official version)
Page: https://openlegislation.uk/lake-lothing-lowestoft-third-crossing-order-2020/schedule-13/paragraph-18
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.