(1) The promoter must at all times on being given reasonable notice allow reasonable facilities to the engineer for access to any specified work during its construction; but such facilities for access are subject to the promoter’s reasonable requirements for ensuring the safety of the railway and of the engineer and other persons working on the railway.
(2) The promoter must supply the engineer with all such information as the engineer may reasonably require with regard to any specified work or the method of constructing it.

---