# The Leeds Railway Station (Southern Entrance) Order 2013, Paragraph 6

Extent: E+W

Where so required by the engineer the promoter must, to the reasonable satisfaction of the engineer, fence off any specified work or protective work or take such other steps as the engineer may require to be taken for the purpose of separating a specified work or a protective work from the relevant part of the waterway, whether on a temporary or permanent basis or both.

---
Source: https://www.legislation.gov.uk/uksi/2013/1933/schedule/15/paragraph/6 (the official version)
Page: https://openlegislation.uk/leeds-railway-station-southern-entrance-order-2013/schedule-15/paragraph-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.