# The Leicestershire County Council (Ashby de la Zouch Canal Extension) Order 2005, Paragraph 11


Subject to paragraph 12, if within a reasonable period, being not less than 28 days from the date when a notice under paragraph 10 is served upon the undertaker, it has failed to begin to take steps to comply with the requirements of the notice or thereafter to make reasonably expeditious progress towards their implementation, the Environment Agency may execute the works specified in the notice, and any expenditure incurred by it in so doing shall be recoverable from the undertaker.

---