# The Leicestershire County Council (Ashby de la Zouch Canal Extension) Order 2005, Paragraph 8


Any specified work, and any protective works required by the Environment Agency as a condition of its approval under paragraph 4, shall be constructed—
(a) with all reasonable despatch in accordance with the plans approved or deemed to have been approved under this Schedule; and
(b) to the reasonable satisfaction of the Environment Agency;
and any officer of the Environment Agency authorised to act on its behalf for the purpose shall be entitled to watch and inspect the construction of such works.

---
Source: https://www.legislation.gov.uk/uksi/2005/2786/schedule/10/paragraph/8 (the official version)
Page: https://openlegislation.uk/leicestershire-county-council-ashby-de-la-zouch-canal-extension-order-2005/schedule-10/paragraph-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.