Regulation 2 Provisions of the Levelling-up and Regeneration Act 2023 coming into force on 18th February 2026
The following provisions of the Levelling-up and Regeneration Act 2023 come into force on 18th February 2026 for compulsory purchase orders to which paragraph (2) applies—
section 183 (conditional confirmation), so far as not already in force;
section 184 (corresponding provision for purchases by Ministers), so far as it relates to the provisions of Schedule 19 brought into force by paragraph (d);
paragraphs 2 to 7 of Schedule 18 (conditional confirmation and making of compulsory purchase orders: consequential amendments), so far as not already in force;
paragraph 3 of Schedule 19 (compulsory purchase: corresponding provision for purchases by Ministers), so far as not already in force.
Paragraph 2(1) applies to compulsory purchase orders that are—
subject to confirmation under Part 2 of the Acquisition of Land Act 1981 by a confirming authority other than the Welsh Ministersf1, or
prepared in draft under paragraph 1 of Schedule 1 to that Act by an acquiring authority other than the Welsh Ministers.
Annotations
Footnotes
- f1
-
See article 2 of, and Schedule 1 to, the National Assembly for Wales (Transfer of Functions) Order 1999 (S.I. 1999/672) which transferred various functions of a Minister of the Crown, including under the Acquisition of Land Act 1981 (c. 67), to the National Assembly for Wales and paragraph 30 of Schedule 11 to the Government of Wales Act 2006 (c. 32) which transferred those functions to the Welsh Ministers.