  "url": "https://openlegislation.uk/little-crow-solar-park-order-2022/schedule-2/paragraph-13",
  "json_url": "https://openlegislation.uk/little-crow-solar-park-order-2022/schedule-2/paragraph-13.json",
  "legislation": "uksi/2022/436",
  "legislation_title": "The Little Crow Solar Park Order 2022",
  "legislation_url": "https://openlegislation.uk/little-crow-solar-park-order-2022",
  "path": "schedule/2/paragraph/13",
  "kind": "paragraph",
  "number": "13",
  "heading": "Archaeology",
  "text": "(1) The authorised development must be carried out in accordance with the archaeological management plan.\n(2) No phase of the authorised development is to be commenced until the archaeological exclusion zone around Gokewell Priory shown on the Archaeological Exclusion Zone – Whole Area Plan (document reference 2.22 LC DRW) has been installed as shown on the works plan.\n(3) No digging or use of piled mounting frames shall be undertaken within the archaeological “no-dig” zone identified on the Works Details – Key B2 - Sheet 5 of 7 (document reference 2.15 LC DRW).\n(4) No phase within the authorised development is to be commenced until a written scheme for the investigation of areas of archaeological interest within that phase has been submitted to and approved by the local planning authority.\n(5) The scheme approved under sub-paragraph (4) must be in accordance with the archaeological management plan and identify any areas where a programme of archaeological investigation is required and the measures to be taken to protect, record or preserve any significant archaeological remains that may be found.\n(6) Any archaeological works or programme of archaeological investigation carried out under the approved scheme for investigation must be carried out by an organisation registered with the Chartered Institute for Archaeologists or by a member of that Institute.\n(7) Any archaeological works or programme of archaeological investigation must be carried out in accordance with the scheme approved under sub-paragraph (4).\n(8) Within six months of the commencement of the authorised development the undertaker must submit a scheme to the local planning authority detailing proposals for two interpretation boards explaining the significance of Gokewell Priory. The scheme shall include details of the proposed location, size, materials, content, means of fixing and maintenance of the proposed boards. The scheme shall be implemented as approved within six months following the completion of the authorised development or six months following the approval of the scheme whichever is the later.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 2 para. 13 in force at 27.4.2022, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2022/436/schedule/2/paragraph/13",
    "retrieved_at": "2026-10-28T22:01:11.831022+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}