{
  "url": "https://openlegislation.uk/little-crow-solar-park-order-2022/schedule-2/paragraph-15",
  "json_url": "https://openlegislation.uk/little-crow-solar-park-order-2022/schedule-2/paragraph-15.json",
  "legislation": "uksi/2022/436",
  "legislation_title": "The Little Crow Solar Park Order 2022",
  "legislation_url": "https://openlegislation.uk/little-crow-solar-park-order-2022",
  "path": "schedule/2/paragraph/15",
  "kind": "paragraph",
  "number": "15",
  "heading": "Operational noise",
  "text": "(1) No phase of the authorised development is to commence until an operational noise assessment containing details of how the design of the authorised development has incorporated mitigation to ensure the operational noise rating levels as set out in the environmental statement are to be complied with for that phase has been submitted to and approved by the local planning authority.\n(2) The authorised development must be implemented and operated for its duration in accordance with the approved operational noise assessment.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 2 para. 15 in force at 27.4.2022, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2022/436/schedule/2/paragraph/15",
    "retrieved_at": "2026-10-28T22:01:11.831022+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}