# The Little Crow Solar Park Order 2022, Paragraph 9: Construction Traffic Management Plan (CTMP)

Extent: E+W+S

(1) No phase of the authorised development is to be commenced until a CTMP covering th at phase and in accordance with the outline CTMP has been submitted to and approved by the local planning authority.
(2) The CTMP must include details of—
(a) associated traffic movements; including delivery vehicles and staff/construction vehicle movements;
(b) traffic management requirements on the adjoining public highway of the B1208, B1207 and the A18; and
(c) a condition survey for any road which will be affected by undertaking that phase of the authorised development and a further condition survey following that phase of the construction works. In the event that any defects are identified in that condition survey that are directly attributable to that phase of the construction works of the authorised development, details of how those defects are to be remediated by the undertaker.
(3) The CTMP must be implemented as approved.

---
Source: https://www.legislation.gov.uk/uksi/2022/436/schedule/2/paragraph/9 (the official version)
Page: https://openlegislation.uk/little-crow-solar-park-order-2022/schedule-2/paragraph-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.