Regulation 2 Amendment of the principal Regulations
In regulation 3 (application) of the principal Regulations, for paragraphs (2) and (3) substitute the following–
“(2)In relation to works of new construction, these Regulations apply to a works contract entered into on or after 1st October 1999 and to functional work to be carried out on or after that date.
(3)In relation to,
(a)general highway works;
(b)the construction or maintenance of a sewer; and
(c)works of maintenance,
these Regulations apply to a works contract entered into on or after 1st January 2000 and to functional work to be carried out on or after that date.”f1.
Annotations
Footnotes
- f1
-
The terms “works contract”, “functional work”, “works of new construction”, “general highway works” and “works of maintenance” are defined or explained in the principal Regulations.