Where on the date of its transfer under article 3 an estate or part of an estate, in respect of which the Greater London Council's own direct labour organisation is carrying out the work of construction, has not been completed, the Greater London Council shall complete the work of construction in accordance with instructions by the Architect to the Greater London Council, for the time being, or such other person or persons as the Greater London Council shall nominate for that purpose, and the completion of the work of construction shall be deemed to have taken place and the Greater London Council to have satisfied the requirements of this article on the day that the said Architect or other nominated person, as the case may be, issues a certificate to the effect that in his opinion the work of construction has been completed and that any defects, shrinkages or other faults, which in his opinion it is proper for the Greater London Council to make good, have been made good.