# The London Gateway Port Harbour Empowerment Order 2008, Paragraph 16

Extent: E+W+S

Once constructed—
(a) no part of the water frontage of the authorised works may be used other than for the berthing of vessels; and
(b) no part of the water frontage of the authorised works between Coordinates Reference 1 and Coordinates Reference 7 as shown on Sheet No. 216 of the deposited plans may be used for the berthing of container vessels or roll-on roll-off ships.

---
Source: https://www.legislation.gov.uk/uksi/2008/1261/schedule/2/paragraph/16 (the official version)