# The London Gateway Port Harbour Empowerment Order 2008, Paragraph 11

Extent: E+W+S

No more than 157,000m2 of B1(b), B1(c), B2 and B8 development shall be first occupied in combination with the bringing into beneficial use of the Ro-Ro or, alternatively, 1 berth without the Ro-Ro, prior to the completion of the following works—
(a) The Sorrells/A1014 junction works;
(b) a Toucan Crossing on Springhouse Road at its junction with Manorway East;
(c) improvements as approved by the appropriate authority to the two pedestrian subways at The Manorway; and
(d) noise mitigation works for the new Sorrells roundabout as approved by the appropriate authority.

---