# The London Gateway Port Harbour Empowerment Order 2008, Paragraph 8

Extent: E+W+S

If—
(a) by reason of the construction of any tidal work it is reasonably necessary for the PLA to incur costs in temporarily or permanently altering, removing, re-siting, repositioning or reinstating existing moorings or aids to navigation (including navigation marks or lights) owned by the PLA, or laying down and removing substituted moorings or buoys, or carrying out dredging operations for any such purpose, not being costs which it would have incurred for any other reason; and
(b) the PLA gives to the Harbour Authority not less than 28 days’ notice of its intention to incur such costs, and takes into account any representations which the Harbour Authority may make in response to the notice within 14 days of the receipt of the notice,
the Harbour Authority shall pay the costs reasonably so incurred by the PLA.

---
Source: https://www.legislation.gov.uk/uksi/2008/1261/schedule/8/paragraph/8 (the official version)
Page: https://openlegislation.uk/london-gateway-port-harbour-empowerment-order-2008/schedule-8/paragraph-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.