# The London Luton Airport Expansion Development Consent Order 2025, Paragraph 22: Monitoring of permitted operations

Extent: E+W

(1) The undertaker must, in accordance with the Monitoring Plans, monitor noise, air quality, greenhouse gas emissions and surface access from at least 1 year prior to the date that notice is served under article 44(1) (interaction with the LLAOL planning permission).
(2) The undertaker must prepare and submit to the ESG—
(a) the first Monitoring Report—
(i) on the date notice is served under article 44(1) (interaction with LLAOL planning permission); and
(ii) no later than 31 July in the calendar year in which that notice is served; and
(b) all subsequent Monitoring Reports on or before 31 July annually thereafter.
(3) Monitoring Reports submitted under sub-paragraph (2) must be prepared in accordance with the Monitoring Plans, which may be amended in accordance with sub-paragraph (5).
(4) Monitoring Plans in respect of noise must include details of dispensed movements for the previous 12 months, including reasons for the dispensation and what measures, if appropriate, would be introduced to reduce these incidents in the future.
(5) The undertaker and the ESG may agree to amend the Monitoring Plans, and such agreement must not be unreasonably withheld.
(6) The undertaker must make a Monitoring Report publicly available as soon as reasonably practicable following submission under sub-paragraph (2).

---
Source: https://www.legislation.gov.uk/uksi/2025/463/schedule/2/paragraph/22 (the official version)
Page: https://openlegislation.uk/london-luton-airport-expansion-development-consent-order-2025/schedule-2/paragraph-22
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.