# The London Luton Airport Expansion Development Consent Order 2025, Paragraph 43: Interpretation

Extent: E+W

In this Part of this Schedule—
“Part 5 consultee” means one or more of the following bodies on matters relating to their function, where that body is not already the discharging authority or a consultee under the relevant paragraph in Part 1, Part 2 or Part 4 of this Schedule—
(a) Buckinghamshire Council;
(b) Central Bedfordshire Council;
(c) Dacorum Borough Council;
(d) the Environment Agency;
(e) Hertfordshire County Council;
(f) Historic England;
(g) Luton Borough Council;
(h) National Highways;
(i) Natural England;
(j) North Hertfordshire District Council;
(k) the relevant sewerage undertaker; and
(l) the relevant water undertaker;
“specified period” means a period of—
(a) 13 weeks for any application under paragraph 6 (detailed design) of Part 2 of this Schedule for detailed design approval of Works Nos. 3b(01), 3b(02), 3d, 3f, 3g and 4a;
(b) 8 weeks for all other applications for approval under Part 1, Part 2 or Part 4 of this Schedule; or
(c) such longer period as may be agreed between the undertaker and the discharging authority.

---
Source: https://www.legislation.gov.uk/uksi/2025/463/schedule/2/paragraph/43 (the official version)