# The London Luton Airport Expansion Development Consent Order 2025, Paragraph 43: Interpretation

Extent: E+W

In this Part of this Schedule—
“Part 5 consultee” means one or more of the following bodies on matters relating to their function, where that body is not already the discharging authority or a consultee under the relevant paragraph in Part 1, Part 2 or Part 4 of this Schedule—
Buckinghamshire Council;
Central Bedfordshire Council;
Dacorum Borough Council;
the Environment Agency;
Hertfordshire County Council;
Historic England;
Luton Borough Council;
National Highways;
Natural England;
North Hertfordshire District Council;
the relevant sewerage undertaker; and
the relevant water undertaker;
“specified period” means a period of—
13 weeks for any application under paragraph 6 (detailed design) of Part 2 of this Schedule for detailed design approval of Works Nos. 3b(01), 3b(02), 3d, 3f, 3g and 4a;
8 weeks for all other applications for approval under Part 1, Part 2 or Part 4 of this Schedule; or
such longer period as may be agreed between the undertaker and the discharging authority.

---
Source: https://www.legislation.gov.uk/uksi/2025/463/schedule/2/paragraph/43 (the official version)
Page: https://openlegislation.uk/london-luton-airport-expansion-development-consent-order-2025/schedule-2/paragraph-43/enacted
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.