Before commencing any specified works, the undertaker must—
(a) provide to the relevant highway authority the detailed design information relating to those specified works and obtain the relevant highway authority’s written approval for those works; and
(b) secure road space booking from the relevant highway authority, such road space booking approval not to be unreasonably withheld or delayed.

---
Source: https://www.legislation.gov.uk/uksi/2025/463/schedule/8/paragraph/55 (the official version)