# The London Underground (East London Line Extension) Order 1997, Schedule 8: LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN


(1)
(2)
(3)
Area
Number of land shown on deposited plans
Purpose for which temporary possession may be taken inconnection with the authorised works
London borough of Hackney
65a and 91a
For the provision of a working site and access for construction purposes and provision of a temporary footpath
London borough of Hackney
114a and 114b
For the provision of access for construction purposes
London borough of Hackney
132 and 133
For the provision of a working site and access for construction purposes
London borough of Hackney
275a and 288
For the provision of a working site and access for construction purposes
London borough of Tower Hamlets
45b, 46b, 50b, 53b, 53c, 55c, 55d, 56b, 56c, 59b and 67a
For the provision of a working site and access for construction purposes
London borough of Lewisham
8 and 9
For the provision of a working site and access for construction purposes

---
Source: https://www.legislation.gov.uk/uksi/1997/264/schedule/8 (the official version)
Page: https://openlegislation.uk/london-underground-east-london-line-extension-order-1997/schedule-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.