# The London Underground (Northern Line Extension) Order 2014, Article 36: Time limit for exercise of powers of acquisition

Extent: E+W+S

(1) After the end of the period of 5 years beginning with the day on which this Order comes into force—
(a) no notice to treat is to be served under Part 1 of the 1965 Act, as applied to the acquisition of land by article 24 (application of Part 1 of the 1965 Act); and
(b) no declaration is to be executed under section 4 (execution of declaration) of the Compulsory Purchase (Vesting Declarations) Act 1981, as applied by article 25 (application of the Compulsory Purchase (Vesting Declarations) Act 1981).
(2) The powers conferred by article 30 (temporary use of land for construction of works) cease at the end of the period referred to in paragraph (1); but nothing in this paragraph prevents LUL from remaining in possession of land after the end of that period, if the land was entered and possession of it was taken before the end of that period.

---
Source: https://www.legislation.gov.uk/uksi/2014/3102/article/36 (the official version)
Page: https://openlegislation.uk/london-underground-northern-line-extension-order-2014/article-36
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.