# The London Underground (Northern Line Extension) Order 2014, Paragraph 85

Extent: E+W+S

Any dispute arising between LUL and the MMO under this Part of this Schedule is to be determined by arbitration under article 48 (arbitration) if the parties agree, but otherwise is to be determined by the Secretary of State for Environment, Food and Rural Affairs and the Secretary of State for Transport acting jointly on a reference to them by LUL or the MMO, after giving notice in writing by one to the other.

---
Source: https://www.legislation.gov.uk/uksi/2014/3102/schedule/8/paragraph/85 (the official version)
Page: https://openlegislation.uk/london-underground-northern-line-extension-order-2014/schedule-8/paragraph-85
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

