# London Underground (Safety Measures) Act 1991, Works at London Bridge


In Greater London—
In the London borough of Southwark—
Work No. 1 A railway (507 metres in length) being a deviation of the existing southbound railway of the Northern Line, commencing by a junction with that railway beneath the river Thames at a point 153 metres north-east of the junction of London Bridge and Montagu Close and terminating by a junction with that railway beneath a point 82 metres north-east of the junction of Union Street and Borough High Street.
Work No. 2 A new ticket hall and subway (135 metres in length), including an escalator subway, commencing beneath a point 24 metres south-west of the junction of Bedale Street and Borough High Street and terminating beneath a point 21 metres north of the junction of London Bridge Street and Borough High Street.
Work No. 3 A subway (89 metres in length) commencing by a junction with an existing subway beneath a point 27 metres east of the junction of London Bridge Street and Borough High Street and terminating by a junction with the Northern Line southbound station tunnel beneath a point 83 metres north-east of the junction of those streets.
Work No. 4 A subway (26 metres in length) commencing by a junction with Work No. 3 beneath a point 44 metres north-east of the junction of London Bridge Street and Borough High Street and terminating by a junction with the Northern line southbound station tunnel beneath a point 53 metres north-east of the junction of those streets.
Work No. 5 A subway (26 metres in length) commencing by a junction with Work No. 2 at a point 23 metres south-west of the junction of St. Thomas Street and Borough High Street and terminating in the footway of Borough High Street at a point 32 metres south-west of the junction of those streets.
Work No. 6 A subway (27 metres in length) commencing by a junction with Work No. 2 at a point 34 metres south-west of the junction of St. Thomas Street and Borough High Street and terminating in Southwark Street at a point 60 metres south-west of the junction of those streets.
Work No. 7 A sewer (154 metres in length) being a diversion of part of the Battlebridge sewer commencing by a junction with that sewer beneath a point 27 metres north of the junction of London Bridge Street and Borough High Street and terminating by a junction with that sewer beneath a point 55 metres south-west of the junction of St. Thomas Street and Borough High Street.
Work No. 8 A subway including a shaft (90 metres in length) commencing at a point 90 metres south-west of the junction of Southwark Street and Stoney Street and terminating by a junction with Work No. 1 beneath a point 25 metres south-east of the junction of those streets.

---
Source: https://www.legislation.gov.uk/ukla/1991/18/schedule/1/crossheading/works-at-london-bridge (the official version)
Page: https://openlegislation.uk/london-underground-safety-measures-act-1991/schedule-1/crossheading-works-at-london-bridge
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.