In relation to a work which is a speciﬁed work because of its proximity to or effect on a sewer, the plans to be submitted to the speciﬁed undertaker under paragraph 20 shall be detailed plans describing—
(a) the exact position of the speciﬁed work;
(b) the level at which it is proposed to be constructed or renewed;
(c) the manner of its construction or renewal;
(d) the position of all sewers within 15 metres of the speciﬁed work or upon which the speciﬁed work will impose a load; and
(e) by way of detailed drawings, every alteration proposed to be made to any such sewer.

---