# The Longfield Solar Farm Order 2023, Schedule 11: LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

Extent: E+W+S

(1)
Plot reference number shown on the Land Plans
(2)
Purpose for which temporary possession may be taken
Land Plans – Sheet 1
1/1B/1
Temporary use as construction laydown areas (Work No. 4B)
1/2A/2/1
Temporary use as construction laydown areas (Work No. 4B)
1/2D
Temporary use as construction laydown areas, works to facilitate access, and temporary overhead line alterations including two new temporary pylons and realignment of the existing 400kV overhead line. (Work Nos. 7B, 9 and 5B)
Land Plans – Sheet 2
2/1B/1
Temporary use as construction laydown areas (Work No. 4B)
2/1B/2
Temporary use as construction laydown areas (Work No. 4B)
2/1B/3
Temporary use as construction laydown areas (Work No. 4B)
2/1E/1
Temporary use as construction laydown areas (Work No. 4B)
2/6/1
Temporary use as construction laydown areas (Work No. 4B)

---
Source: https://www.legislation.gov.uk/uksi/2023/734/schedule/11 (the official version)
Page: https://openlegislation.uk/longfield-solar-farm-order-2023/schedule-11
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.