# The Longfield Solar Farm Order 2023, Paragraph 1: Commencing an arbitration

Extent: E+W+S

(1) The primary objective of these arbitration rules is to achieve a fair, impartial, final and binding award on the substantive difference between the parties (save as to costs) within 4 months from the date the arbitrator is appointed pursuant to article 39 of this Order.
(2) The arbitration is deemed to have commenced when a party (“the claimant”) serves a written notice of arbitration on the other party (“the respondent”).

---
Source: https://www.legislation.gov.uk/uksi/2023/734/schedule/14/paragraph/1 (the official version)
Page: https://openlegislation.uk/longfield-solar-farm-order-2023/schedule-14/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.