# The Longfield Solar Farm Order 2023, Paragraph 102


(1) Subject to sub-paragraph (2), any specified work, and all protective works required by ESW under paragraph 101, must be constructed—
(a) without unreasonable delay in accordance with the plans approved or deemed to have been approved or settled under this Part of this Schedule; and
(b) to the reasonable satisfaction of ESW,
and an officer of ESW is entitled to watch and inspect the construction of such works.
(2) The undertaker must give to ESW—
(a) not less than 28 days’ notice in writing of its intention to commence construction of any specified work; and
(b) notice in writing of its completion not later than seven days after the date on which it is brought into use.

---
Source: https://www.legislation.gov.uk/uksi/2023/734/schedule/15/paragraph/102 (the official version)
Page: https://openlegislation.uk/longfield-solar-farm-order-2023/schedule-15/paragraph-102
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.