# The Longfield Solar Farm Order 2023, Paragraph 15: Construction traffic management plan

Extent: E+W+S

(1) No phase of the solar farm works and grid connection works may commence until a construction traffic management plan (which must be substantially in accordance with the framework construction traffic management plan) for that phase has been submitted to and approved by the relevant planning authority for that phase or, where the phase falls within the administrative areas of both the Braintree District Council and Chelmsford City Council, both relevant planning authorities, such approval to be in consultation with National Highways and the relevant highway authority.
(2) The construction traffic management plan must be implemented as approved.

---
Source: https://www.legislation.gov.uk/uksi/2023/734/schedule/2/paragraph/15 (the official version)
Page: https://openlegislation.uk/longfield-solar-farm-order-2023/schedule-2/paragraph-15
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.