# The Luton Dunstable Translink Order 2006, Schedule 2: ACQUISITION OF CERTAIN LAND


(1)
(2)
(3)
Area
Number of land shown on deposited plans
Purpose for which land may be acquired
County of Bedfordshire
District of South Bedfordshire
1, 2
Provision of stopping places and access for construction and operation of the authorised works
6
Relocation of electricity pylons and working site
8
Provision of access
9
Provision of exchange land
20, 23
Provision of access for construction and operation of the authorised works
24, 26, 27, 28, 35, 36, 37, 37a, 38, 39
Provision of highway modification
25
Provision of bus turnaround
42, 43, 44, 80
Provision of access for construction and maintenance
58a
Provision of ecological mitigation works
91, 92
Provision of temporary working site, access and ecological mitigation works
Borough of Luton
1, 2, 4, 6, 35, 36, 37, 61, 62, 63, 85, 153, 156, 159
Provision of access for construction and maintenance
51, 56
Provision of access for construction and modification of structures
98
Modification to accommodate removal of existing structure
104, 105, 106, 106a, 107
Provision of pedestrian access
126, 127, 128
Provision of drainage
162
Provision of stopping places and construction and operation of authorised works

---
Source: https://www.legislation.gov.uk/uksi/2006/3118/schedule/2 (the official version)
Page: https://openlegislation.uk/luton-dunstable-translink-order-2006/schedule-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.