Article 10 As to Parkend Crossing
The Company may in the construction of Railway No. 5 carry the same with a double line of rails across and on the level of the Yorkley Road immediately north of Parkend station.
The Company shall erect and at all times maintain good and sufficient gates across the Company’s railway at each side of the highway at the crossing of the highway at Parkend crossing, and in connection with such level crossing the provisions set out in Schedule 4 to this Order shall apply.
Nothing in this Order shall require the provision of any building or keeper at Parkend crossing.
Subject to the provisions of this Order the Company may, during and for the purpose of the execution of the works for the purposes of or in connection with Parkend crossing, stop up and divert and interfere with temporarily all or any part of the carriageway or footway of the highway within the area of the level crossing and may for any reasonable time divert the traffic therefrom and prevent all persons other than those going bona fide to any premises abutting on the highway from passing along and using the same.
The Company shall provide reasonable access for persons on foot going bona fide to any such premises.
The Company shall not exercise the powers of this article without the consent of the County Council.
Any such consent may be given subject to such reasonable conditions as the County Council may require but shall not be unreasonably withheld and any question whether such consent has been unreasonably withheld, or whether any such condition is reasonable, shall be referred to and determined by a single arbitrator to be agreed upon between the parties or, failing such agreement, to be appointed by the President for the time being of the Institution of Civil Engineers on the application of either party (after notice in writing has been given to the other party).