# The M1 Junction 10a (Grade Separation) Order 2013, Article 19: Time limits for exercise of authority to acquire land compulsorily and to use land temporarily

Extent: E+W+S

(1) After the end of the period of 5 years beginning on the day on which this Order comes into force—
(a) no notice to treat is to be served under Part 1 of the 1965 Act; and
(b) no declaration is to be executed under section 4 of the Compulsory Purchase (Vesting Declarations) Act 1981 as applied by article 22 (application of the Compulsory Purchase (Vesting Declarations) Act 1981).
(2) The authority conferred by article 25 (temporary use of land for carrying out the authorised development) ceases at the end of the period referred to in paragraph (1), except that nothing in this paragraph prevents the undertaker remaining in possession of land after the end of that period, if the land was entered and possession was taken before the end of that period.

---
Source: https://www.legislation.gov.uk/uksi/2013/2808/article/19 (the official version)
Page: https://openlegislation.uk/m1-junction-10a-grade-separation-order-2013/article-19
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.