# The M20 Junction 10a Development Consent (Amendment) Order 2019, Note: Explanatory note


(This note is not part of the Order)
This Order amends the M20 Junction 10a Development Consent Order 2017 (S.I. 2017/1202).
This Order is made following an application made in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 for a non-material change under paragraph 6 of Schedule 2 to the Planning Act 2008 in relation to the specified days and hours of work which the construction environmental management plan must require adherence to.
This Order makes provision to permit works which are exclusively earthworks to be carried out on Sundays and Bank Holidays between the hours of 08:00 and 17:00 and the extension of working hours on other days by one hour (to 19:00) on Mondays to Fridays and by five hours (to 18:00) on Saturdays.

---
Source: https://www.legislation.gov.uk/uksi/2019/1271/note (the official version)
Page: https://openlegislation.uk/m20-junction-10a-development-consent-amendment-order-2019/note
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.