# The M20 Junction 10a Development Consent Order 2017, Paragraph 14: Flood compensatory storage

Extent: E+W+S

(1) No part of the authorised development is to commence until a detailed flood compensatory storage scheme is submitted to and approved in writing by the Secretary of State, following consultation with the relevant planning authority.
(2) The scheme prepared under sub-paragraph (1) must provide suitable flood storage for any flood waters that would be displaced by the authorised development in the 1 in 100 year plus 105% climate change allowance event.
(3) The scheme must be fully implemented as approved and subsequently maintained.

---
Source: https://www.legislation.gov.uk/uksi/2017/1202/schedule/2/paragraph/14 (the official version)
Page: https://openlegislation.uk/m20-junction-10a-development-consent-order-2017/schedule-2/paragraph-14
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.