# The M25 Junction 10/A3 Wisley Interchange Development Consent Order 2022, Part 1: SPECIAL ROADS

Extent: E+W

(1)
Highway
(2)
Extent
M25 eastbound
Improved M25 eastbound carriageway, as shown between points 10/1 and 10/2 on Sheet 10 of the streets, rights of way and access plans, comprising 40 metres and between point 10/3 on Sheet 10 and point 18/2 on Sheet 18 of the streets, rights of way and access plans, comprising 5,580 metres.
M25 eastbound on-slip at M25 junction 10
Altered slip road, as shown between point 5/20 on Sheet 5 and point 14/2 on Sheet 14 of the streets, rights of way and access plans, comprising 955 metres.
M25 eastbound off-slip at M25 junction 10
Improved slip road, as shown between point 11/2 on Sheet 11 and point 5/12 on Sheet 5 of the streets, rights of way and access plans, comprising 900 metres.
M25 westbound
Improved M25 westbound carriageway, as shown between point 18/1 on Sheet 18 and point 10/4 on Sheet 10 of the streets, rights of way and access plans, comprising 6,050 metres.
M25 westbound on-slip at M25 junction 10
Improved slip road, as shown between point 5/9 on Sheet 5 and point 11/1 on Sheet 11 of the streets, rights of way and access plans, comprising 1,225 metres.
M25 westbound off-slip at M25 junction 10
Altered slip road, as shown between point 14/1 on Sheet 14 and point 5/21 on Sheet 5 of the streets, rights of way and access plans, comprising 800 metres.
A3 northbound to M25 westbound dedicated free-flow slip lane at M25 junction 10
New slip lane, as shown between point 5/3 on Sheet 5 and point 12/5 on Sheet 12 of the streets, rights of way and access plans, comprising 205 metres.
M25 eastbound to A3 northbound dedicated free-flow slip lane at M25 junction 10
New slip lane, as shown between point 12/4 on Sheet 12 and point 5/15 on Sheet 5 of the streets, rights of way and access plans, comprising 225 metres.
A3 southbound to M25 eastbound dedicated free-flow slip lane at M25 junction 10
New slip lane, as shown between point 5/18 on Sheet 5 and point 13/1 on Sheet 13 of the streets, rights of way and access plans, comprising 210 metres.
M25 westbound to A3 southbound dedicated free-flow slip lane at M25 junction 10
New slip lane, as shown between point 13/2 on Sheet 13 and point 5/4 on Sheet 5 of the streets, rights of way and access plans, comprising 250 metres.

---
Source: https://www.legislation.gov.uk/uksi/2022/549/schedule/3/part/1 (the official version)